2. The ESCO performs a Technical Audit and proposes utility Cost Saving Measures (CSM). This process is completed.
3. The UI selects a package of CSMs and negotiates a Performance Contract with the ESCO to implement the CSMs. This process is currently underway. Negotiations for a campus wide lighting package were completed, a Heating Ventilation and Air Conditioning package is close to completion, and a central utility system package is currently in the design stage.
4. The ESCO implements the project at a guaranteed cost with guaranteed CSM performance, and provides savings verification over life of contract. The lighting upgrade package is currently under construction.